Second Storey Addition: Costs, Approvals and Design

Writer: Andrew Lynch
Andrew Lynch
Nov 18
9 min read

Brisbane home with an integrated second storey

A second storey addition lets you keep your block, your street and your garden while doubling your floor area. It only works when the existing house can carry the new level, and that is settled before anyone draws a floor plan. The right order is structure first, then design, then approval, then price. A building designer who knows Brisbane’s rules and construction can run that sequence for you, which is what we do at Formardå for homeowners across the city.



TL;DR

 

  • Whether your footings, walls and roof can take a new level decides the design, the budget and sometimes whether going up is sensible at all.

  • Published builder guides put second storey construction at roughly $3,000 to $10,000+ per square metre, depending on finish, before design, engineering and approval fees.

  • In Brisbane you need building approval from a licensed certifier, and planning approval too if the design doesn’t meet the City Plan’s acceptable outcomes.

  • Good plans show the structure, the staircase, the services and the neighbours’ sunlight, not just the new rooms.

  • Allow six to nine months from first sketch to handover, longer if the footings need strengthening.

 

Table of Contents

 

 

Is your house able to carry a second storey?

 

The first question is not what the upstairs will look like. It is what the downstairs can support. A guide to second storey additions in Australia says the central issue is whether the existing foundation and ground-floor structure can carry the added load. That takes a structural engineer’s assessment, not a visual guess.

 

Four things get checked, and none can be assumed from the age of the house, according to a structural engineering firm’s footing guide:

 

  1. The footings. Their width, depth and reinforcement, and what they sit on. Test pits dug at two or three spots confirm it.

  2. The soil. Its site classification under AS 2870, the Australian Standard for residential slabs and footings, which rates how much clay swells and shrinks with moisture.

  3. The walls. Single-skin brick, cavity brick and timber frame carry extra load differently. Corroded wall ties in cavity brick weaken the wall.

  4. The floor and roof structure. Existing ceiling joists were never sized as floor joists, so they are almost always replaced.

 

Reading the soil class

 

AS 2870 classes run from A (stable sand or rock, effectively no movement) through S, M, H1 and H2 to E, which is extremely reactive and moves more than 75 mm, as a geotechnical guide explains. The same guide cautions that a soil report written for a two-storey dwelling is generally not suitable for a taller building. The report has to be commissioned for the work you actually propose.

 

What the findings can change

 

Three results change a project most, according to the same footing guide:

 

  • Undersized footings. The fix is widening or underpinning, which is far better found in a test pit than in a crack six months after handover.

  • Poor founding material. Footings sitting on fill rather than natural ground may need piles down to competent material, which changes the budget significantly.

  • Limited wall capacity. Where masonry can’t take the load, a lightweight timber or steel upper level with light cladding can bring loads back within what the house can carry, and may save the footing work entirely.

 

Older homes are the usual suspects. Timber-framed houses on stumps from the 1950s to the 1970s often need significant foundation upgrading, and strengthening can involve underpinning, new concrete footings or replacing stumps. If you own a lowset brick home or a raised timber house in Brisbane, expect this conversation early.

 

Warning signs to mention to your engineer

 

One builder’s foundation guide lists diagonal cracks wider than 2 mm, doors that rub after heavy rain and patch repairs on the slab edge as signs a home may need extra structural work. Note them down before the engineer visits. The same guide adds that skipping structural sign-off can lead to stop-work notices under the Building Act and void warranty insurance.


Diagonal crack in an older home's exterior wall

What does a second storey addition cost?

 

Costs vary widely, so treat any single figure with caution. One Australian guide gives construction-only ranges of $3,000 to $4,500 per square metre for a standard finish, $4,500 to $6,500 mid-range and $6,500 to $10,000+ for premium. On its numbers, a 60 to 80 m² addition lands between $180,000 and $360,000, and 80 to 120 m² between $360,000 and $600,000.


Second-storey addition cost ranges by finish and area

For Brisbane specifically, one local builder reports that most extensions in 2025 cost $3,500 to $4,800 per square metre for standard projects, with second storey additions between $350,000 and $800,000+. Another 2025 cost guide puts a simple 60 to 80 m² addition at $350,000 to $550,000. These are builders’ published ranges for those years, not quotes. Your own figure comes from documented plans.

 

Costs beyond construction

 

The same Australian guide lists the extras that sit outside the per-square-metre rate:

 

Item

Typical range

Structural engineering

$3,000 to $15,000

Architect or designer fees

$15,000 to $60,000 (typically 8% to 12% of construction cost)

Development application and building permit fees

$3,000 to $15,000

Temporary accommodation

$15,000 to $50,000

 

Where budgets blow out

 

Existing services were not designed for a second level. Plumbing, electrical and air-conditioning extensions can take 10% to 15% of the budget, and a bigger switchboard, a larger hot water system and a new staircase all add up. For older Brisbane homes, asbestos removal, old wiring or plumbing, temporary relocation and mid-build design changes are the usual surprises. Local builders advise a 10% to 15% contingency, and one guide suggests up to 20%.

 

The cheapest protection is settling the structure and the design before pricing. Changes after construction starts cost far more than changes on paper.

 

Will it add value?

 

Builders often claim large value gains from going up, but the figure depends on your suburb, the quality of the build and what the house is worth without it. A second storey that adds bedrooms and living space to a well-located block tends to appeal because you keep the address. A sound way to test your own numbers is to compare the total project cost with sale prices of larger homes on similar blocks in your street. A local agent’s appraisal is the right authority on that.

 

Approvals for a second storey in Brisbane

 

Approval rules are set by state and council, so what applies in Brisbane is different from Sydney or Perth. Brisbane City Council says extensions and renovations need building approval from a licensed building certifier. Planning approval is also required when the project doesn’t meet all the acceptable outcomes of the Brisbane City Plan 2014 dwelling house code (or the small lot code), and neighbourhood plan areas and overlays add further criteria.

 

In plain terms there are two questions:

 

  • Planning: is the building the right size and shape for the site? Height, setbacks, site cover and character overlays (many inner suburbs have traditional building character protections) sit here.

  • Building: is it structurally sound, safe and compliant with the building code? A private certifier or council inspector checks this.

 

The Australian Government’s YourHome guide notes that changes to plumbing, drainage, gas and electrical work also need approval and inspection by the relevant authority. A second storey touches all of them.

 

Brisbane City Council also says a certifier needs scaled, detailed plans prepared by a draftsperson or architect. That is the documentation stage a building designer prepares. Our own guides cover the local detail: do you need council approval in Brisbane and how we help with DA approvals.

 

How long approvals take

 

One guide suggests assessment of a straightforward development application commonly takes six to sixteen weeks, including neighbour notification and assessment against height, setbacks, overshadowing and neighbourhood character. Whether you need a development application at all depends on whether your design meets the acceptable outcomes. Designing within them from the start is the quickest route.

 

What good second floor addition plans include

 

A second storey is more than a box on top. The plans a certifier and your neighbours see should cover:

 

  • Structural drawings. Footings, beams, columns and the way the new load travels down to the ground, signed off by an engineer.

  • Site plan and elevations. Showing height, setbacks and how the new level looks from the street.

  • Shadow diagrams. Councils commonly ask for these. Inner West Council, for example, requires shadow diagrams that show in separate colours the shadows from existing and proposed buildings, including fences and neighbouring buildings. Even where a drawing isn’t compulsory, overshadowing is what neighbours object to first.

  • Staircase position. The stair eats floor area on both levels and can force a reshuffle of the ground floor.

  • Services layout. Where plumbing stacks, air-conditioning and the switchboard will run.

  • Privacy and views. Window placement, screening and balconies so the new level does not look straight into next door.

 

Making the new level work with the old house

 

The best second storey additions look as if the house was always designed that way. That means matching roof forms, rooflines and materials to the existing house, or choosing a deliberate contrast. It also means planning the ground floor: a new stair usually takes a bedroom or hallway space, so the downstairs is often partly renovated at the same time.

 

For character homes, the approach differs. Queenslanders can often be built under or raised rather than topped with a heavy second level, and character overlays shape what is allowed. Our Queenslander renovation guide covers those options.

 

Light structure, lighter bill

 

Weight matters. As noted above, a lightweight timber or steel frame with light cladding can keep loads within the existing structure’s capacity, sometimes avoiding footing work. Design choices like this are a reason to involve a designer before an engineer finalises anything, not after.

 

How the project runs and what to expect at home

 

One Gold Coast builder’s phase-by-phase timeline gives a realistic picture for a second storey: feasibility two to four weeks, engineering and detailed design two to three weeks, approvals four to eight weeks, then construction. The total is six to nine months from first sketch to handover. Underpinning, flood studies or major facade upgrades push it toward the upper end.

 

The practical sequence looks like this:

 

  1. Feasibility and brief. Decide what you need upstairs: bedrooms, a parents’ retreat, a home office, a bathroom.

  2. Structural and soil investigation. Test pits and a soil classification for the work proposed.

  3. Concept design. Layout, stair position, street appearance and a rough cost check.

  4. Documentation. Detailed drawings and engineering, ready for the certifier.

  5. Approvals. Building approval, plus planning approval where the design needs it.

  6. Tender and construction. Roof removal, framing, weatherproofing, services, linings and fit-out.

 

The roof comes off early, so the build is weather-sensitive and noisy. Many families move out for the roof and framing stages, which is why temporary accommodation appears in the cost table above. Others stay and live downstairs, which needs a clear plan for dust, water and power from day one.

 

How we approach second storey projects

 

Formardå is a Brisbane building design and drafting studio led by licensed designer Andrew Lynch, and we have been designing since 2009. Our work blends creative design with practical construction knowledge, so the new level is both good-looking and compliant with local regulations, and we offer building approval management as part of our services.

 

If you’re weighing up going up, our renovations and extensions design service is the starting point. We work with homeowners to turn the brief into plans that suit the house, the site and Brisbane’s planning rules.


Formarda

To talk through your house and what you want upstairs, see our building designer page or our full list of services.

 

FAQ

 

Can any house take a second storey?

 

Not automatically. The footings, soil, walls and roof structure all have to be assessed by an engineer, and older homes often need strengthening. Some houses can go up with a lightweight upper level that keeps the added load within existing capacity.

 

How long does a second storey addition take?

 

Plan on six to nine months from first sketch to handover, based on a published phase timeline. Approvals alone can take several weeks, and footing work, flood studies or heavy facade changes extend the program.

 

Do I need council approval in Brisbane?

 

You need building approval from a licensed certifier. You also need planning approval if the design doesn’t meet the acceptable outcomes of the Brisbane City Plan 2014 dwelling house code, as Brisbane City Council explains. Overlays and neighbourhood plans add criteria in some suburbs.

 

How much contingency should I allow?

 

Brisbane builders advise a 10% to 15% buffer for surprises like asbestos, old wiring or design changes. Settling structure and design before construction starts keeps the buffer from being used up.

 

Is a second storey cheaper than moving?

 

That depends on your block, your suburb and the build. Add the construction range, professional fees, approvals and temporary accommodation, then compare the total with the price of a comparable larger home in your area, including stamp duty and moving costs.

 