Building Plans Approval in Australia: How the Process Works

Writer: Andrew Lynch
Andrew Lynch
5 days ago
9 min read

Certifier inspecting timber framing at a Brisbane home

Building plans approval in Australia is two separate decisions. The first is whether the land can be used or developed the way you propose, which is usually the council’s call. The second is whether the building itself is safe and meets the building code, which is a certifier’s call in Queensland. Plans that are drawn with both tests in mind go through faster. Plans drawn only to look good tend to come back with information requests. At Formardå, a Brisbane building design studio, we prepare plans for both tests from the first sketch, which is why this guide follows that sequence.



TL;DR

 

  • Planning (development) approval and building approval are different processes with different rules, and some projects need only one of them.

  • In Queensland, councils handle planning under their local schemes. A licensed building certifier assesses the plans against the building code, inspects the work and signs off occupation.

  • You need every required approval before work starts. In NSW, a construction certificate issued after work has begun is invalid.

  • Timeframes vary by state and pathway: NSW fast-track approvals can take as little as 20 days, while WA statutory periods are 10 to 25 business days.

  • Complete, dimensioned, code-aware plans are the single biggest lever you control over how smoothly approval goes.

 

Table of Contents

 

 

Planning approval and building approval are not the same thing

 

Most confusion on this topic comes from the word “approval” covering two systems.

 

Planning approval (called development approval in Queensland) looks at the proposal against the local planning scheme. Southern Midlands Council describes it as mainly concerned with impacts on neighbouring land: privacy, overshadowing, setbacks, height, use, streetscape and parking.

 

Building approval checks the design against the building code and plumbing rules. The same council page lists sound construction, fire protection, light and ventilation, drainage and user safety. Inspections may follow at various construction stages.

 

The Queensland Government fact sheet (reviewed August 2023) puts it the same way. A development approval is needed before starting assessable development and is issued by the local government. A building approval confirms the building complies with building laws, and it is achieved through a registered building certifier, ending with a Certificate of Occupancy.


Comparison of Queensland planning and building approvals

The Tasmanian State Planning Commission notes the two sit under entirely separate legislation. There, a planning permit must be issued first (where one is required) before building approval can be given.

 

What the Building Code of Australia is called now

 

The Building Code of Australia (BCA) now sits inside the National Construction Code (NCC). The ABCB explains that the BCA is Volumes One and Two of the NCC, and the Plumbing Code of Australia is Volume Three. When a certifier says your plans must comply with the NCC, they mean the same rulebook people used to call the BCA.

 

Who grants which approval

 

The split of responsibilities differs by state, so check the rules where the site is.

 

Queensland. The QBCC explains that councils manage planning, zoning and development rules under each local planning scheme. Building certifiers assess and approve plans, inspect work at key stages, issue certificates of inspection and give the final approval so a building can be legally occupied. Most of the time the builder engages the certifier, but the owner can choose their own.

 

New South Wales. The NSW Government says you may need development consent from your council, or a fast-track Complying Development Certificate issued by the council or a registered certifier. Where consent applies, a construction certificate must be issued before work starts and a principal certifier appointed.

 

Western Australia. The Shire of Toodyay states that starting building work without a building permit is an offence under the Building Act 2011. Permits are generally required for residential, commercial and industrial structures, including alterations, additions, pools, spas and sheds, subject to listed exemptions.

 

Tasmania. Small, low-risk structures such as decks and small sheds may not need a building permit.

 

The common thread: even where a project seems minor, check before you start. Our own page on whether you need council approval in Brisbane covers the local question.


Who grants which approval

What counts as development in Queensland

 

The Queensland fact sheet lists what is assessable development needing a development application: building work, plumbing or drainage work, operational work, reconfiguring a lot (subdividing), a material change of use, clearing native vegetation and demolition. Accepted development does not need a development application, though a building approval may still be required.

 

In practice, this means a renovation can need three layers: council sign-off on the planning side (for example, a front setback or a heritage character overlay), a certifier’s building approval, and then inspections through construction. A new home, a hospitality fit-out and a multi-residential build each trigger these layers differently, which is why a reader planning a commercial or hospitality project should settle the approval path before design is locked.

 

The steps in Queensland, and where each one goes wrong

 

The Queensland fact sheet sets out four steps for building approval. Here they are, with the problems that tend to cost time.

 

1. Prepare the building plans

 

The fact sheet advises preparing plans and seeking advice from architecture or engineering firms. This is the step that decides everything after it. Plans need to carry enough information that the certifier can judge compliance and a builder can build from them. The ACT’s building approval guideline states the principle plainly: finished dimensions, arrangement, locations and material characteristics must be clear enough for a certifier to check compliance and for a competent builder to build.

 

Where it goes wrong: a design that ignores setbacks, site coverage or height limits can be redrawn after the council or certifier flags it. Plans with missing dimensions or unclear materials draw requests for more information.

 

This is the step where a building designer earns their fee. Formardå is led by licensed designer Andrew Lynch, and our approach combines creative design with practical construction knowledge so the plans are built to be compliant for the site. Our drafting services produce the documentation set.

 

2. Apply for building approval

 

You apply to the local government or an accredited building certifier who knows the Building Act, the NCC and the Queensland Development Code. The Gold Coast City Council notes that Queensland building approvals are usually issued by private certifiers, licensed by the QBCC. Other agencies may receive a copy of the application, and the council may weigh in on matters like setbacks.

 

Where it goes wrong: lodging the building application before the development approval conditions are settled. A certifier cannot issue approval until other required approvals are in place, so sequencing matters.

 

3. Approval to start, then inspections

 

Once satisfied, the certifier grants approval to commence construction. They then inspect during construction and collect compliance forms. Your builder works to the approved plans, so any change on site that departs from them needs to go back through the certifier.

 

4. Certificate of Occupancy

 

When the certifier is satisfied the work is complete and suitable for occupation, they issue the Certificate of Occupancy. You cannot legally occupy a new building until then.

 

The fact sheet is clear that you must hold the development approval (where applicable) and the building approval before commencing construction. NSW is just as firm: a construction certificate issued after work has started is invalid, and an occupation certificate will not be issued.

 

Documents a building approval application needs

 

Exact lists differ by council, state and building class, but the pattern is consistent.

 

In Brisbane. Brisbane City Council requires DA Form 1 (application details) for code or impact assessable applications, DA Form 2 for building work, written and dated owner’s consent, proposal plans, a planning assessment and any specialist investigation reports.

 

A national benchmark. The Australian Building Codes Board’s design acceptance guidance recommends minimum documentation that includes:

 

  • site identification and conditions, and a site plan with confirmed boundaries and setbacks

  • the building’s Class, Type and Importance Level

  • an NCC Performance Requirement Checklist showing whether you follow the deemed-to-satisfy path or a performance solution

  • fully dimensioned construction drawings and specifications

  • declarations and certificates of design compliance

 

In plain terms, a deemed-to-satisfy solution follows the code’s prescribed methods. A performance solution proves by other means that the design meets the code’s goals. The ABCB also recommends that, at least for higher-risk commercial buildings (classes 2 to 9), one building practitioner is responsible for the complete design documentation at approval stage.

 

ACT example. The ACT’s minimum documentation rules require a residential site plan at a scale of at least 1:200, showing building position and dimensions, driveways, parking, finished site levels and boundary relationships.

 

The lesson for owners and developers: a thin set of drawings is the most common reason an assessment stalls. Brisbane City Council notes that an information request extends the assessment timeframe, and a decision notice follows within five business days of completed assessment.

 

How long approval takes

 

There is no single national timeframe. Some published figures show the range:

 

State

Pathway

Published timeframe

NSW

Complying development (fast-track)

As little as 20 days

NSW

Pattern Book pathway

10 days

NSW

Development application (average)

70 days

WA

Certified building permit

10 business days

WA

Uncertified permit (class 1a and 10)

25 business days

NSW figures come from the NSW planning authority, and the 70-day figure is an average, not a guarantee. The WA periods are from the Shire of Toodyay, where the clock starts the day after a complete application is received. Applicants must supply additional information within 21 days of a written request to avoid refusal.

 

Two things follow. First, the clock runs only on a complete application, so documentation quality shapes the real timeline. Second, rules and codes change. The NSW planning pages and your state’s building authority are the place to confirm the current pathway and any new code edition before you lodge.

 

Fees also vary by state and by the value of the work. Ask your council or certifier for the current fee schedule when you have a cost estimate.

 

Why the design stage decides the approval stage

 

A good approval outcome is largely decided before anything is lodged. Three habits make the difference:

 

  1. Check the planning overlays first. Character, heritage, flooding and setback controls shape what can be drawn. Our Queenslander renovation guide shows how this plays out on older Brisbane homes.

  2. Draw to the code from the start. Choosing the compliance pathway and dimensioning everything fully avoids information requests.

  3. Keep one party responsible for the whole document set. Fragmented drawings from several consultants are where inconsistencies creep in.

 

If you are weighing up who should prepare your plans, our page on building designer versus architect sets out the difference.

 

How Formardå handles approvals for Brisbane projects

 

Formardå is a Brisbane building design and drafting studio, working since 2009 on residential, commercial and hospitality projects. Building approval management is one of the services we offer, alongside design, drafting and documentation, so the same team that draws the project understands what the approval needs. You can read how we approach development application support.


Formarda

Whether you are planning a renovation or extension, a new home, or a commercial or hospitality project, start with a conversation about the site and what you want to build. See all of our building design services.

 

FAQ

 

Do I need both council approval and building approval?

 

Not always, but often. Planning or development approval deals with how land is used and developed. Building approval deals with whether the construction meets the building code. A project can need one, both or neither, depending on its size, location and your state’s rules, so confirm before you start.

 

Who approves building plans in Queensland?

 

A licensed building certifier assesses and approves the building plans, and the council handles planning matters under its local scheme. Most of the time the builder engages the certifier, but the owner can choose their own, according to the QBCC.

 

What happens if I start building before approval?

 

It is a serious problem. In WA it is an offence to start building work without a permit. In NSW, a construction certificate issued after work begins is invalid and an occupation certificate will not be issued. Get all required approvals first.

 

Are approved building plans the end of the process?

 

No. Approval lets construction start. The certifier then inspects at key stages, and a final certificate is needed before the building can legally be occupied. The builder must work to the approved plans.

 

Sources

 